CRE Screen – Shipped: April 23, 2018
CRE1804-1: Negative
CRE1804-2: Positive
CRE1804-3: Positive
CRE1804-4: Positive
Participants’ results
Challenge Expected Results Positive Negative
CRE1804-1 Negative 15 (Acceptable)
CRE1804-2 Positive 15 (Acceptable)
CRE1804-3 Positive 15 (Acceptable)
CRE1804-4 Positive 15 (Acceptable)
CMPT QC/QA/Statistics:
Samples, CRE 1804-2, -3 and -4, were CRE positive and sample, CRE 1804-1, was CRE negative. All samples were homogenous and stable for 16 days from the date of production, April 17, 2018.
All samples were produced by CMPT. Samples were randomly selected for QC/QA. Statistics are not applicable in qualitative surveys. CMPT results are listed in the above table.